Contract and Project Procurement

Welcome to the Contract and Project Procurement Exam

You have 2hrs to write this exam, Good luck.

The number of attempts remaining is 2

1 / 50

1. Which of the answers best define Procurement?

2 / 50

56. When do we spot buy?

3 / 50

What is the process of identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan? 4

4 / 50

What type of market has very few sellers, where the actions of one seller will have a direct effect on the other seller’s prices?

5 / 50

55. All of these are objectives of negotiation except?

6 / 50

7. Compete the following : In STAGE 6 of the Cycle stage, price evaluation including

7 / 50

Which of the following is NOT a stage of team development?

8 / 50

84. All of the following are QMS principle except.

9 / 50

57. Periodic contract is needed when the exact future requirement can be forecasted….

10 / 50

50. Business cycle, Money supply, inflation, Unemployment, Disposable income, Energy availability & cost are all under?

11 / 50

25. Companies should be registered with the following agency.

12 / 50

Which type of matrix organization gives the project manager low authority?

13 / 50

Which motivation theory states that management believes that workers will do as little as possible to get by?

14 / 50

What type of forecast looks for a cause-and-effect relationship to predict demand?

15 / 50

Which conflict resolution technique involves pushing one’s viewpoint at the expense of others?

16 / 50

65. Procurement professionals with strategic management skill can advise organization on the following except

17 / 50

3. How many key roles of procurement were discussed?

18 / 50

60. Multiple sourcing includes all the following except

19 / 50

53. Under the characteristics of procurement and buying method, which includes ‘The aim is to obtain the best price for the suppliers’.

20 / 50

What project management process includes the processes that organize, manage, and lead the project team?

21 / 50

Which is NOT a common contract type?

22 / 50

What does “terms and conditions” include?

23 / 50

95. Inventory cost involves all the follow except.

24 / 50

What is the safety stock quantity plus predicted demand during the anticipated lead time?

25 / 50

36. Importer receives the cargo?

26 / 50

48. One of the main functions of supply management is to…

27 / 50

Which conflict resolution technique involves retreating from an actual or potential conflict situation?

28 / 50

29. The PAAR is issued and the importer does what?

29 / 50

80. One of the many advantage of ……. Is, it is customer focused. It seeks to offer quality from the point of view of the customer.

30 / 50

What type of project management office (PMO) provides project management support functions?

31 / 50

4. The tendering Procedure includes the following except

32 / 50

In which organizational structure does each employee have one clear superior?

33 / 50

8. What STAGE in the Cycle stage, is the Contract Signature?

34 / 50

22. The NCS maintains a fast track window through which select importers may forward their cargoes directly to their warehouses where custom procedures such as examination and payments are undertaken.

35 / 50

34. Terminal operator handles, Terminal handling, loading of cargo, Issues bills for handling and rent.

36 / 50

11. Procurement function in Nigeria, in Import and Export is to receive clearance for goods imported into Nigeria.

37 / 50

94. How many types of human mistake was discussed?

38 / 50

What is an agreement that is executed between two or more parties, that can include terms such as payments, proposals, and procurement statement of work?

39 / 50

Which of the following is NOT a key role of the project manager in procurement?

40 / 50

37. Procurement deals with the following

41 / 50

76. All of these are benefit of procurement planning except.

42 / 50

Who typically signs a contract?

43 / 50

41. …….. Is impartial, consistent and therefore reliable.

44 / 50

93. All of this are purpose of lean management except.

45 / 50

62. Suppliers that have expressed interest are required to complete a pre-qualification questionnaire in the following.

46 / 50

42. Accountability is at once a key Inducement to individual and institutional probity, a key deterrent to collusion and corruption and key perquisite to procurement credibility. This process is known as what in procurement?

47 / 50

90. All of these are ways of improving communication except.

48 / 50

70. …….. Is important in our everyday life because we are stuck in finding solution to common problem.

49 / 50

Which type of organizational chart is a traditional structure that can be used to show positions and relationships in a graphic, top-down chart?

50 / 50

In which organizational structure are units arranged by the types of projects they do?